Google’s plan to build a massive AI data center in Pine Island, Minnesota, faces a new round of regulatory scrutiny after a lawsuit settlement placed the project’s environmental review under state supervision. The agreement requires Google and developer Ryan Companies to disclose more information about the facility’s water and electricity demands before construction can start.
The settlement is the first time Minnesota’s Pollution Control Agency (MPCA) will oversee the environmental assessment of a data center. Previous reviews of these facilities have been handled by local governments.
The proposed development, known as Project Skyway, encompasses a 482-acre technology campus near Rochester. Google plans to develop an 88-acre portion of the property that includes a 250,000-square-foot data center.
For Google, the Pine Island settlement preserves the possibility of construction but adds regulatory requirements. The project’s future now depends on whether its environmental assessment and mitigation measures are enough for state regulators and local officials.
Challenging the Approval Process
The Minnesota Center for Environmental Advocacy (MCEA) challenged Pine Island’s initial approval process, arguing that officials had failed to adequately evaluate the project’s environmental impact. The organization filed suit last October and secured a temporary restraining order in May that halted work.
Under the settlement, approved unanimously by the Pine Island City Council, MCEA will drop its lawsuits while the developers undergo a more extensive environmental assessment. The review will examine at least 16 environmental and community issues, including electricity consumption, water requirements, noise and light pollution. Google and Ryan Companies must also develop measures to address potential problems and submit those plans for regulatory and municipal approval.
The process includes a 60-day public comment period, with notices mailed to residents throughout the 55963 ZIP code. Previous city agreements with the developers remain valid. The extra oversight is likely to extend the project’s timeline.
Additionally, there’s concern about the cost of supplying electricity to the facility. Minnesota Attorney General Keith Ellison has questioned whether an electricity agreement between Google subsidiary Echo Zone LLC and Xcel Energy could shift substantial costs to other utility customers. Ellison warned that the agreement could leave other Xcel customers facing additional electricity costs potentially exceeding $1 billion.
Ellison also criticized the companies for withholding financial details in regulatory filings, limiting public scrutiny of the agreement.
Xcel disputed the attorney general’s characterization, maintaining that Google would cover its own costs. The competing claims highlight the difficulty of determining who ultimately pays for infrastructure needed to support large AI computing facilities.
Google and Ryan Companies have welcomed the settlement. Ryan Companies senior VP Peter Fitzgerald said the developer was satisfied that existing city approvals would remain intact.
For environmental advocates, the agreement offers a model for broader regulation of hyperscale computing facilities. MCEA CEO Kathryn Hoffman has argued that water consumption and electricity infrastructure extend beyond municipal boundaries, making state expertise essential to assessing large data center proposals.
The dispute, to be sure, aligns with wider resistance to data center development across Minnesota. In Hermantown, protesters recently prevented a city council vote on another proposed Google facility. Police declared an unlawful assembly after demonstrators disrupted proceedings, and a subsequent meeting was canceled. Separately, opposition has led to litigation over a proposed Farmington facility and the rejection of a project in Worthington.